Eskom logo. PHOTO: Supplied/Eskom website

Business In The News South Africa

Eskom’s Medupi Unit 5 achieves Commercial Operation ahead of schedule

OHANNESBURG, April 3 – Eskom, on Monday said they were pleased to announce that Unit 5 at its Medupi Power Station Project in Lephalale, Limpopo, has attained Commercial Operation status.

The unit was officially declared commercial after the completion of control performance and the 72-hour reliability tests, putting all performance guarantees to effect.

” Unit 5 was first synchronised to the national grid on September 2016. This was then followed by further testing and optimising which resulted in its full power of 800 MW being attained on December 2016,” Interim Group Chief Executive, Matshela Koko said in a statement.

Koko said this came ahead of the scheduled time line of March 2018. With an output of 800 MW going to the national grid, Unit 5 joined its sister unit, Unit 6, which has been contributing to the balancing of electricity supply and demand since August 2015.

The remarkable progress came after intensive continuous testing activities and shared dedication from Eskom and its execution partners.

“The Eskom new build programme is meant for strengthening the electricity supply, Medupi with its second unit coming online, is a reflection of the endeavours towards realising this initiative, Eskom applauds the Medupi team, this milestone is indeed an epitome of delivery.”

Koko said Commercial Operation status ensures technical compliance to statutory, safety and legal requirements. This signatory milestone marks the contractual handover of the unit from the primary contractors to Eskom, which means that Medupi Unit 5 is now part of the Eskom Generation fleet.

– African News Agency (ANA)